Utility

Ensuring robust utility support including air, power, and steam systems for uninterrupted and efficient plant performance.

Gantt Chart for Utility

Day 01

16/04/2026

Rakho Boiler Cleaning And furness Dust Removing. Shifting And Dumping Yard Boiler Back Side.Boiler Heavy Wood Cutting Starting.

17/04/2026

Boiler Feed Water 2 Tanks Cleaning Working Proces.2″ Condenser Water Pipe Line And Wall Checking . Heavy Wood Working Proces .

18/04/2026

Boiler Feed Water 2 Tanks Cleaning Working Proces.2″ Condenser Water Pipe Line And Wall Checking .Over Head Tank To Direct Water New Line.

19/04/2026

Boiler Feed Water 2 Tanks Cleaning Working Proces.3″ Over Head Gate wall Replecing New One .Heavy Wood Working Proces

20/04/2026

Boiler Feed Water 2 Tanks Copleted. Z Venteletor Work Sample In MC Hall Completed.DRF Duct Bend Removing Working Proces.

21/04/2026

Boiler All Walls Open & Servecing Working Proces.Pre heaters Two Sump Cleaning Working Process.Condenser Water Line 2″ Line Working Process.

22/04/2026

  • Total Planned Activity : 35nos
  • Ongoing Activity : 7 Nos
  • Completed Activity : 3
  • Percentage Completion : 8.6%
  • SPI – Scheduled Performance Index : 1.5

23/04/2026

  • Total Planned Activity : 35 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 3
  • Percentage Completion : 8.6%
  • SPI – Scheduled Performance Index : 1.5

24/04/2026

  • Total Planned Activity : 35 nos
  • Ongoing Activity : 5 Nos
  • Completed Activity : 3
  • Percentage Completion : 8.6%
  • SPI – Scheduled Performance Index : 2.2

25/04/2026

  • Total Planned Activity : 35 nos
  • Ongoing Activity : 4 Nos
  • Completed Activity : 3
  • Percentage Completion : 8.6%
  • SPI – Scheduled Performance Index : 2.1

27/04/2026

  • Total Planned Activity : 35 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity :3
  • Percentage Completion : 8.6%
  • SPI – Scheduled Performance Index : 1.9

28/04/2026

  • Total Planned Activity :35 nos
  • Ongoing Activity : 4 Nos
  • Completed Activity :3
  • Percentage Completion : 8.6%
  • SPI – Scheduled Performance Index : 1.9

29/04/26

  • Total Planned Activity : 35 nos
  • Ongoing Activity : 4
  • Completed Activity : 3
  • Percentage Completion : 8.6%
  • SPI – Scheduled Performance Index : 2.1

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

30/04/26

  • Total Planned Activity : 35 nos
  • Ongoing Activity : 4
  • Completed Activity : 3
  • Percentage Completion : 8.6%
  • SPI – Scheduled Performance Index : 2.0

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

02/05/26

  • Total Planned Activity : 35 nos
  • Ongoing Activity : 3
  • Completed Activity : 3
  • Percentage Completion : 8.6%
  • SPI – Scheduled Performance Index : 1.9

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

04/05/26

  • Total Planned Activity : 35 nos
  • Ongoing Activity : 3
  • Completed Activity :3
  • Percentage Completion :8.6%
  • SPI – Scheduled Performance Index : 1.7

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

05/05/26

  • Total Planned Activity : 35 nos
  • Ongoing Activity : 3
  • Completed Activity : 3
  • Percentage Completion : 8.6%
  • SPI – Scheduled Performance Index : 1.6

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

06/05/26

  • Total Planned Activity : 35 nos
  • Ongoing Activity : 4
  • Completed Activity : 4
  • Percentage Completion : 11.4%
  • SPI – Scheduled Performance Index : 1.5

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedul

07/05/26

  • Total Planned Activity : 35 nos
  • Ongoing Activity : 4
  • Completed Activity : 4
  • Percentage Completion :11.4%
  • SPI – Scheduled Performance Index : 1.5

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

08/05/26

  • Total Planned Activity : 35 nos
  • Ongoing Activity : 4
  • Completed Activity : 4
  • Percentage Completion : 11.4%
  • SPI – Scheduled Performance Index : 1.4

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

09/05/26

  • Total Planned Activity : 35 nos
  • Ongoing Activity : 4
  • Completed Activity : 4
  • Percentage Completion : 11.4%
  • SPI – Scheduled Performance Index : 1.3

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

11/05/26

  • Total Planned Activity : 35 nos
  • Ongoing Activity : 2
  • Completed Activity : 4
  • Percentage Completion : 11.4%
  • SPI – Scheduled Performance Index : 1.4

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

12/05/26

  • Total Planned Activity : 35 nos
  • Ongoing Activity : 2
  • Completed Activity : 11
  • Percentage Completion : 31.4%
  • SPI – Scheduled Performance Index : 1.5

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

13/05/26

  • Total Planned Activity : 35 nos
  • Ongoing Activity : 2
  • Completed Activity : 11
  • Percentage Completion : 31.4%
  • SPI – Scheduled Performance Index : 1.4

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

14/05/26

  • Total Planned Activity : 36 nos
  • Ongoing Activity : 3
  • Completed Activity : 12
  • Percentage Completion : 33.3%
  • SPI – Scheduled Performance Index : 0.26

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

15/05/26

  • Total Planned Activity : 36 nos
  • Ongoing Activity :
  • Completed Activity : 12
  • Percentage Completion : 33.3%
  • SPI – Scheduled Performance Index : 0.27

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

16/05/26

  • Total Planned Activity : 36 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 13
  • Percentage Completion : 36.1%
  • SPI – Scheduled Performance Index : 0.28

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

18/05/26

  • Total Planned Activity : 36 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 13
  • Percentage Completion : 36.1%
  • SPI – Scheduled Performance Index : 0.35

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

19/05/26

  • Total Planned Activity : 36 nos
  • Ongoing Activity : 2
  • Completed Activity : 13
  • Percentage Completion : 36.1%
  • SPI – Scheduled Performance Index : 0.36

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

20/05/26

  • Total Planned Activity : 36 nos
  • Ongoing Activity : 2
  • Completed Activity : 13
  • Percentage Completion : 36.1%
  • SPI – Scheduled Performance Index : 0.36

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

21/05/26

  • Total Planned Activity : 36 nos
  • Ongoing Activity : 3
  • Completed Activity : 14
  • Percentage Completion : 38.9%
  • SPI – Scheduled Performance Index : 0.40

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

22/05/26

  • Total Planned Activity : 36 nos
  • Ongoing Activity :
  • Completed Activity : 14
  • Percentage Completion : 38.9%
  • SPI – Scheduled Performance Index : 0.40

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

23/05/26

  • Total Planned Activity : 36 nos
  • Ongoing Activity : 2
  • Completed Activity : 14
  • Percentage Completion : 38.9%
  • SPI – Scheduled Performance Index : 0.41

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

25/05/26

  • Total Planned Activity : 36 nos
  • Ongoing Activity : 2
  • Completed Activity : 14
  • Percentage Completion : 38.9%
  • SPI – Scheduled Performance Index : 0.43

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

26/05/26

  • Total Planned Activity : 36 nos
  • Ongoing Activity : 2
  • Completed Activity : 14
  • Percentage Completion : 38.9%
  • SPI – Scheduled Performance Index : 0.44

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

27/05/26

  • Total Planned Activity : 36 nos
  • Ongoing Activity : 2
  • Completed Activity : 14
  • Percentage Completion : 38.9%
  • SPI – Scheduled Performance Index : 0.44

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

29/05/26

  • Total Planned Activity : 36 nos
  • Ongoing Activity : 2
  • Completed Activity : 14
  • Percentage Completion : 38.9%
  • SPI – Scheduled Performance Index : 0.47

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

30/05/26

  • Total Planned Activity : 36 nos
  • Ongoing Activity : 2
  • Completed Activity : 14
  • Percentage Completion : 38.9%
  • SPI – Scheduled Performance Index : 0.47

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

01/06/26

  • Total Planned Activity : 36 nos
  • Ongoing Activity : 2
  • Completed Activity : 14
  • Percentage Completion : 38.9%
  • SPI – Scheduled Performance Index : 0.57

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

02.06.26

  • Total Planned Activity : 36
  • Ongoing Activity : 2
  • Completed Activity : 14
  • Percentage Completion : 39%
  • SPI – Scheduled Performance Index : 0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

03.06.26

  • Total Planned Activity : 36
  • Ongoing Activity : 2
  • Completed Activity : 14
  • Percentage Completion :39%
  • SPI – Scheduled Performance Index :0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

04.06.26

  • Total Planned Activity : 36
  • Ongoing Activity : 2
  • Completed Activity : 14
  • Percentage Completion : 39%
  • SPI – Scheduled Performance Index :0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

05.06.26

  • Total Planned Activity : 36
  • Ongoing Activity : 2
  • Completed Activity : 14
  • Percentage Completion :39%
  • SPI – Scheduled Performance Index : 0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

06.06.26

  • Total Planned Activity : 36
  • Ongoing Activity : 2
  • Completed Activity :14
  • Percentage Completion : 39%
  • SPI – Scheduled Performance Index : 0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

08.06.26

  • Total Planned Activity : 36
  • Ongoing Activity : 2
  • Completed Activity : 14
  • Percentage Completion : 39%
  • SPI – Scheduled Performance Index :0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)