Electricals

Comprehensive electrical works including cabling, panels, load distribution, and commissioning

Gantt Chart for Electricals

Day 01

16/04/2026

  • Total Planned Activity : 23 nos
  • Ongoing Activity : 2 Nos
  • Completed Activity : Nil
  • Percentage Completion : 0%
  • SPI – Scheduled Performance Index

17/04/2026

  • Total Planned Activity : 23 nos
  • Ongoing Activity : 2 Nos
  • Completed Activity : Nil
  • Percentage Completion : 0%
  • SPI – Scheduled Performance Index

18/04/2026

  • Total Planned Activity : 23 nos
  • Ongoing Activity : 2 Nos
  • Completed Activity : Nil
  • Percentage Completion : 0%
  • SPI – Scheduled Performance Index

19/04/2026

  • Total Planned Activity : 23 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : Nil
  • Percentage Completion : 0%
  • SPI – Scheduled Performance Index

20/04/2026

  • Total Planned Activity : 23 nos
  • Ongoing Activity : 2 Nos
  • Completed Activity : Nil
  • Percentage Completion : 0%
  • SPI – Scheduled Performance Index

21/04/2026

  • Total Planned Activity : 23 nos
  • Ongoing Activity : 2 Nos
  • Completed Activity : 2
  • Percentage Completion : 8.7%
  • SPI – Scheduled Performance Index

22/04/2026

  • Total Planned Activity : 23 nos
  • Ongoing Activity : 2 Nos
  • Completed Activity : 3
  • Percentage Completion : 13%
  • SPI – Scheduled Performance Index : 1.0

 

23/04/2026

  • Total Planned Activity : 23 nos
  • Ongoing Activity : 2 Nos
  • Completed Activity : 4
  • Percentage Completion : 17.4%
  • SPI – Scheduled Performance Index : 1.7

24/04/2026

  • Total Planned Activity : 23 nos
  • Ongoing Activity : 2 Nos
  • Completed Activity : 4
  • Percentage Completion : 17.4%
  • SPI – Scheduled Performance Index : 2.2

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

25/04/2026

  • Total Planned Activity : 26 nos
  • Ongoing Activity : 2 Nos
  • Completed Activity : 4
  • Percentage Completion : 15.4%
  • SPI – Scheduled Performance Index : 2.1

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

27/04/2026

  • Total Planned Activity : 26 nos
  • Ongoing Activity : 2 Nos
  • Completed Activity : 6
  • Percentage Completion : 23.1%
  • SPI – Scheduled Performance Index : 1.9

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

28/04/2026

  • Total Planned Activity : 26 nos
  • Ongoing Activity : 2 Nos
  • Completed Activity : 6
  • Percentage Completion : 23.1%
  • SPI – Scheduled Performance Index : 1.9

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

29/04/26

  • Total Planned Activity : 26 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 8
  • Percentage Completion : 30.8%
  • SPI – Scheduled Performance Index : 2.1

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

30/04/26

  • Total Planned Activity : 26 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 8
  • Percentage Completion : 30.8%
  • SPI – Scheduled Performance Index : 2.0

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

02/05/26

  • Total Planned Activity : 26 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 8
  • Percentage Completion : 30.8%
  • SPI – Scheduled Performance Index : 1.9

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

04/05/26

  • Total Planned Activity : 26 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 8
  • Percentage Completion : 30.8%
  • SPI – Scheduled Performance Index : 1.7

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

05/05/26

  • Total Planned Activity : 26 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 8
  • Percentage Completion : 30.8%
  • SPI – Scheduled Performance Index : 1.6

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

06/05/26

  • Total Planned Activity : 28 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 8
  • Percentage Completion : 28.6%
  • SPI – Scheduled Performance Index : 1.5

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

07/05/26

  • Total Planned Activity : 28 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 8
  • Percentage Completion : 28.6%
  • SPI – Scheduled Performance Index : 1.5

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

08/05/26

  • Total Planned Activity : 28 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 8
  • Percentage Completion : 28.6%
  • SPI – Scheduled Performance Index : 1.4

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

09/05/26

  • Total Planned Activity : 28 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 8
  • Percentage Completion : 28.6%
  • SPI – Scheduled Performance Index : 1.3

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

11/05/26

  • Total Planned Activity : 28 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 11
  • Percentage Completion : 39.3%
  • SPI – Scheduled Performance Index : 1.4

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

12/05/26

  • Total Planned Activity : 30 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 11
  • Percentage Completion : 36.7%
  • SPI – Scheduled Performance Index : 1.5

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

13/05/26

  • Total Planned Activity : 30 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 11
  • Percentage Completion : 36.7%
  • SPI – Scheduled Performance Index : 1.4

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

14/05/26

  • Total Planned Activity : 30nos
  • Ongoing Activity : 2 Nos
  • Completed Activity : 11
  • Percentage Completion : 36.7%
  • SPI – Scheduled Performance Index : 0.26

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

15/05/26

  • Total Planned Activity : 30 nos
  • Ongoing Activity : 2 Nos
  • Completed Activity : 11
  • Percentage Completion : 36.7%
  • SPI – Scheduled Performance Index : 0.27

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

16/05/26

  • Total Planned Activity : 30 nos
  • Ongoing Activity : 2 Nos
  • Completed Activity : 11
  • Percentage Completion : 36.7%
  • SPI – Scheduled Performance Index : 0.28

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

18/05/26

  • Total Planned Activity : 30 nos
  • Ongoing Activity : 2 Nos
  • Completed Activity : 11
  • Percentage Completion : 36.7%
  • SPI – Scheduled Performance Index : 0.25

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

19/05/26

  • Total Planned Activity : 30nos
  • Ongoing Activity : 2 Nos
  • Completed Activity : 21
  • Percentage Completion : 70%
  • SPI – Scheduled Performance Index : 0.36

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

20/05/26

  • Total Planned Activity : 30 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 21
  • Percentage Completion : 70%
  • SPI – Scheduled Performance Index : 0.35

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

21/05/26

  • Total Planned Activity : 30 nos
  • Ongoing Activity : 2
  • Completed Activity : 21
  • Percentage Completion : 70%
  • SPI – Scheduled Performance Index : 0.40

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

22/05/26

  • Total Planned Activity : 30 nos
  • Ongoing Activity : 2
  • Completed Activity : 21
  • Percentage Completion : 70%
  • SPI – Scheduled Performance Index : 0.40

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

23/05/26

  • Total Planned Activity : 30 nos
  • Ongoing Activity : 2
  • Completed Activity : 21
  • Percentage Completion : 70%
  • SPI – Scheduled Performance Index : 0.41

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

25/05/26

  • Total Planned Activity : 30 nos
  • Ongoing Activity : 2
  • Completed Activity : 21
  • Percentage Completion : 70%
  • SPI – Scheduled Performance Index : 0.43

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

26/05/26

  • Total Planned Activity : 30 nos
  • Ongoing Activity : 2
  • Completed Activity : 21
  • Percentage Completion : 70%
  • SPI – Scheduled Performance Index : 0.44

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

27/05/26

  • Total Planned Activity : 30 nos
  • Ongoing Activity : 2
  • Completed Activity : 21
  • Percentage Completion : 70%
  • SPI – Scheduled Performance Index : 0.44

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

29/05/26

  • Total Planned Activity : 30 nos
  • Ongoing Activity : 2
  • Completed Activity : 21
  • Percentage Completion : 70%
  • SPI – Scheduled Performance Index : 0.47
  •  

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

30/05/26

  • Total Planned Activity : 30 nos
  • Ongoing Activity : 2
  • Completed Activity : 22
  • Percentage Completion : 73.3%
  • SPI – Scheduled Performance Index : 0.47

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

01.06.26

  • Total Planned Activity : 30 nos
  • Ongoing Activity : 2
  • Completed Activity : 21
  • Percentage Completion : 70%
  • SPI – Scheduled Performance Index : 0.57

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

16/04/2026 (Thursday)

  • Total Planned Activity : 42 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : Nil
  • Percentage Completion : 0%
  • SPI – Scheduled Performance Index : 1.0

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

02.06.26

  • Total Planned Activity : 32
  • Ongoing Activity : 2
  • Completed Activity : 29
  • Percentage Completion : 66%
  • SPI – Scheduled Performance Index : 0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

03.06.26

  • Total Planned Activity : 32
  • Ongoing Activity : 2
  • Completed Activity :29
  • Percentage Completion : 66%
  • SPI – Scheduled Performance Index :0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

04.06.26

  • Total Planned Activity : 32
  • Ongoing Activity : 2
  • Completed Activity : 29
  • Percentage Completion : 66%
  • SPI – Scheduled Performance Index :0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

05.06.26

  • Total Planned Activity : 32
  • Ongoing Activity : 2
  • Completed Activity :29
  • Percentage Completion :66
  • SPI – Scheduled Performance Index : 0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

06.06.26

  • Total Planned Activity : 32
  • Ongoing Activity : 2
  • Completed Activity : 29
  • Percentage Completion : 66%
  • SPI – Scheduled Performance Index : 0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)