Butts Line
Enhancing butts processing efficiency through improved cylinder design, separation systems, and uniform material flow.
Gantt Chart for Butts Line
Day 01
16/04/2026 (Thursday)
- Total Planned Activity : 24 nos
- Ongoing Activity : 0 Nos
- Completed Activity : Nil
- Percentage Completion : 0%
- SPI – Scheduled Performance Index : 1.0
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 02
17/04/2026
- Total Planned Activity : 24 nos
- Ongoing Activity : 0 Nos
- Completed Activity : Nil
- Percentage Completion : 0%
- SPI – Scheduled Performance Index :
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 03
18/04/2026
- Total Planned Activity : 24 nos
- Ongoing Activity : 0 Nos
- Completed Activity : Nil
- Percentage Completion : 0%
- SPI – Scheduled Performance Index : 0
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 04
19/04/2026
- Total Planned Activity : 24 nos
- Ongoing Activity : 1 Nos
- Completed Activity : Nil
- Percentage Completion : 0%
- SPI – Scheduled Performance Index :
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 05
20/04/2026
- Total Planned Activity : 24 nos
- Ongoing Activity : 0 Nos
- Completed Activity : Nil
- Percentage Completion : 0%
- SPI – Scheduled Performance Index :
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 06
21/04/2026
- Total Planned Activity : 24 nos
- Ongoing Activity : 0 Nos
- Completed Activity : Nil
- Percentage Completion : 0%
- SPI – Scheduled Performance Index :
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 07
22/04/2026
- Total Planned Activity : 24 nos
- Ongoing Activity : 3 Nos
- Completed Activity : Nil
- Percentage Completion : 0%
- SPI – Scheduled Performance Index : 1.5
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 08
23/04/2026
- Total Planned Activity : 24 nos
- Ongoing Activity : 5 Nos
- Completed Activity : 2
- Percentage Completion : 8.3%
- SPI – Scheduled Performance Index : 1.7
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 09
24/04/2026
- Total Planned Activity : 24 nos
- Ongoing Activity : 8 Nos
- Completed Activity : 6
- Percentage Completion : 15%
- SPI – Scheduled Performance Index : 1.7
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 10
25/04/2026
- Total Planned Activity : 24 nos
- Ongoing Activity : 5 Nos
- Completed Activity : 6
- Percentage Completion : 25%
- SPI – Scheduled Performance Index : 2.1
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 11
27/04/2026
- Total Planned Activity : 24 nos
- Ongoing Activity : 5 Nos
- Completed Activity : 5
- Percentage Completion : 20.8%
- SPI – Scheduled Performance Index : 1.9
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 12
28/04/2026
- Total Planned Activity : 24 nos
- Ongoing Activity : 6 Nos
- Completed Activity : 10
- Percentage Completion :41.7%
- SPI – Scheduled Performance Index : 1.9
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 13
29/04/2026
- Total Planned Activity : 24 nos
- Ongoing Activity : 6 Nos
- Completed Activity : 10
- Percentage Completion : 41.7%
- SPI – Scheduled Performance Index : 2.1
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 14
30/04/2026
- Total Planned Activity : 24 nos
- Ongoing Activity : 6 Nos
- Completed Activity : 10
- Percentage Completion : 41.7%
- SPI – Scheduled Performance Index : 2.0
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 15
02/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 6 Nos
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 1.9
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 16
04/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 6 Nos
- Completed Activity : 12
- Percentage Completion : 50 %
- SPI – Scheduled Performance Index : 1.7
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 17
05/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 8
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 1.6
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 18
06/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 8
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 1.5
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 19
07/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 8 Nos
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 1.5
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 20
08/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 8 Nos
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 1.4
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 21
09/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 8
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 1.3
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 22
11/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 8 Nos
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 1.4
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 23
12/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 8 Nos
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 1.5
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 24
13/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 8 Nos
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 1.4
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 25
14/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 8 Nos
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 0.26
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 26
15/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 8 Nos
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 0.27
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 27
16/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 8 Nos
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 0.28
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 28
18/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 8 Nos
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 0.35
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 29
19/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 8
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 0.36
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 30
20/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 8
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 1.0
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 31
21/05/26
- Total Planned Activity : 24nos
- Ongoing Activity : 8
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 0.40
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 32
22/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 8
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 0.40
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 33
23/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 8 Nos
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 0.40
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 34
25/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 8
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 0.40
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 35
26/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 8
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 0.40
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 36
27/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 9
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 0.44
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 37
29/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 9
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 0.47
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 38
30/05/26
- Total Planned Activity : 24nos
- Ongoing Activity : 9
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 0.47
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 39
01/05/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 9
- Completed Activity : 12
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 0.57
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 40
02/06/26
- Total Planned Activity : 24 nos
- Ongoing Activity : 6
- Completed Activity : 18
- Percentage Completion : 0%
- SPI – Scheduled Performance Index : 1.0
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 41
03.06.26
- Total Planned Activity : 24
- Ongoing Activity : 6 Nos
- Completed Activity : 18
- Percentage Completion : 75%
- SPI – Scheduled Performance Index : 0.62
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 42
04.06.2026
- Total Planned Activity : 24
- Ongoing Activity : 6
- Completed Activity : 18
- Percentage Completion : 75%
- SPI – Scheduled Performance Index :0.62
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 43
05.06.2026
- Total Planned Activity : 24
- Ongoing Activity : 6
- Completed Activity :18
- Percentage Completion : 75
- SPI – Scheduled Performance Index : 0.64
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 44
06.06.2026
- Total Planned Activity : 24
- Ongoing Activity : 6
- Completed Activity :18
- Percentage Completion : 75%
- SPI – Scheduled Performance Index : 0.62
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 45
16/04/2026 (Thursday)
- Total Planned Activity : 42 nos
- Ongoing Activity : 3 Nos
- Completed Activity : Nil
- Percentage Completion : 0%
- SPI – Scheduled Performance Index : 1.0
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)