Butts Line

Enhancing butts processing efficiency through improved cylinder design, separation systems, and uniform material flow.

Gantt Chart for Butts Line

Day 01

16/04/2026 (Thursday)

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 0 Nos
  • Completed Activity : Nil
  • Percentage Completion : 0%
  • SPI – Scheduled Performance Index : 1.0

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

17/04/2026

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 0 Nos
  • Completed Activity : Nil
  • Percentage Completion : 0%
  • SPI – Scheduled Performance Index

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

18/04/2026

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 0 Nos
  • Completed Activity : Nil
  • Percentage Completion : 0%
  • SPI – Scheduled Performance Index : 0

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

19/04/2026

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 1 Nos
  • Completed Activity : Nil
  • Percentage Completion : 0%
  • SPI – Scheduled Performance Index

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

20/04/2026

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 0 Nos
  • Completed Activity : Nil
  • Percentage Completion : 0%
  • SPI – Scheduled Performance Index

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

21/04/2026

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 0 Nos
  • Completed Activity : Nil
  • Percentage Completion : 0%
  • SPI – Scheduled Performance Index

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

22/04/2026

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : Nil
  • Percentage Completion : 0%
  • SPI – Scheduled Performance Index : 1.5

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

23/04/2026

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 5 Nos
  • Completed Activity : 2
  • Percentage Completion : 8.3%
  • SPI – Scheduled Performance Index : 1.7

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

24/04/2026

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 8 Nos
  • Completed Activity : 6
  • Percentage Completion : 15%
  • SPI – Scheduled Performance Index : 1.7

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

25/04/2026

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 5 Nos
  • Completed Activity : 6
  • Percentage Completion : 25%
  • SPI – Scheduled Performance Index : 2.1

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

27/04/2026

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 5 Nos
  • Completed Activity : 5
  • Percentage Completion : 20.8%
  • SPI – Scheduled Performance Index : 1.9

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

28/04/2026

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 6 Nos
  • Completed Activity : 10
  • Percentage Completion :41.7%
  • SPI – Scheduled Performance Index : 1.9

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

29/04/2026

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 6 Nos
  • Completed Activity : 10
  • Percentage Completion : 41.7%
  • SPI – Scheduled Performance Index : 2.1

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

30/04/2026

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 6 Nos
  • Completed Activity : 10
  • Percentage Completion : 41.7%
  • SPI – Scheduled Performance Index : 2.0

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

02/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 6 Nos
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 1.9

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

04/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 6 Nos
  • Completed Activity : 12
  • Percentage Completion : 50 %
  • SPI – Scheduled Performance Index : 1.7

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

05/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 8
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 1.6

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

06/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 8
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 1.5

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

07/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 8 Nos
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 1.5

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

08/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 8 Nos
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 1.4

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

09/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 8
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 1.3

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

11/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 8 Nos
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 1.4

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

12/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 8 Nos
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 1.5

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

13/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 8 Nos
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 1.4

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

14/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 8 Nos
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.26

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

15/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 8 Nos
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.27

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

16/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 8 Nos
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.28

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

18/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 8 Nos
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.35

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

19/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 8
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.36

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

20/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 8
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 1.0

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

21/05/26

  • Total Planned Activity : 24nos
  • Ongoing Activity : 8
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.40

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

22/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 8
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.40

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

23/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 8 Nos
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.40

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

25/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 8
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.40

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

26/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 8
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.40

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

27/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 9
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.44

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

29/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 9
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.47

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

30/05/26

  • Total Planned Activity : 24nos
  • Ongoing Activity : 9
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.47

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

01/05/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 9
  • Completed Activity : 12
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.57

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

02/06/26

  • Total Planned Activity : 24 nos
  • Ongoing Activity : 6
  • Completed Activity : 18
  • Percentage Completion : 0%
  • SPI – Scheduled Performance Index : 1.0

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

03.06.26

  • Total Planned Activity : 24
  • Ongoing Activity : 6 Nos
  • Completed Activity : 18
  • Percentage Completion : 75%
  • SPI – Scheduled Performance Index : 0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

04.06.2026

  • Total Planned Activity : 24
  • Ongoing Activity : 6
  • Completed Activity : 18
  • Percentage Completion : 75%
  • SPI – Scheduled Performance Index :0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

05.06.2026

  • Total Planned Activity : 24
  • Ongoing Activity : 6
  • Completed Activity :18
  • Percentage Completion : 75
  • SPI – Scheduled Performance Index : 0.64

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

06.06.2026

  • Total Planned Activity : 24
  • Ongoing Activity : 6
  • Completed Activity :18
  • Percentage Completion : 75%
  • SPI – Scheduled Performance Index : 0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

16/04/2026 (Thursday)

  • Total Planned Activity : 42 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : Nil
  • Percentage Completion : 0%
  • SPI – Scheduled Performance Index : 1.0

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)