Tipps Line
Optimizing tipping and initial material handling for smooth flow, reduced losses, and consistent feed quality.
Gantt Chart for Tipps Line
Day 01
16/04/2026
- Total Planned Activity : 20 nos
- Ongoing Activity : 1 Nos
- Completed Activity : Nil
- Percentage Completion : 0%
- SPI – Scheduled Performance Index :



Day 02
17/04/2026
- Total Planned Activity : 20 nos
- Ongoing Activity : 1 Nos
- Completed Activity : Nil
- Percentage Completion : 0%
- SPI – Scheduled Performance Index :


Day 03
18/04/2026
- Total Planned Activity : 20 nos
- Ongoing Activity : 2 Nos
- Completed Activity : Nil
- Percentage Completion : 0%
- SPI – Scheduled Performance Index : 1.0



Day 04
19/04/2026
- Total Planned Activity : 20 nos
- Ongoing Activity : 2 Nos
- Completed Activity : Nil
- Percentage Completion : 0%
- SPI – Scheduled Performance Index : 1.0
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 05
20/04/2026
- Total Planned Activity : 20 nos
- Ongoing Activity : 0
- Completed Activity : Nil
- Percentage Completion : 0%
- SPI – Scheduled Performance Index : 1.0
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 06
21/04/2026
- Total Planned Activity : 20 nos
- Ongoing Activity : 0 Nos
- Completed Activity : 1
- Percentage Completion : 0%
- SPI – Scheduled Performance Index : 1.7
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 07
22/04/2026
- Total Planned Activity : 20nos
- Ongoing Activity : 4 Nos
- Completed Activity : 1
- Percentage Completion : 0%
- SPI – Scheduled Performance Index : 1.5
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 08
23/04/2026
- Total Planned Activity : 20nos
- Ongoing Activity : 6 Nos
- Completed Activity : 2
- Percentage Completion : 10%
- SPI – Scheduled Performance Index : 1.7
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 09
24/04/2026
- Total Planned Activity : 20 nos
- Ongoing Activity : 6 Nos
- Completed Activity : 4
- Percentage Completion : 0%
- SPI – Scheduled Performance Index : 1.9
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 10
25/04/2026
- Total Planned Activity : 20 nos
- Ongoing Activity : 4 Nos
- Completed Activity : 4
- Percentage Completion : 20%
- SPI – Scheduled Performance Index : 2.1
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 11
27/04/2026
- Total Planned Activity : 20 nos
- Ongoing Activity : 6 Nos
- Completed Activity : 6
- Percentage Completion : 30%
- SPI – Scheduled Performance Index : 1.9
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 12
28/04/2026
- Total Planned Activity : 20 nos
- Ongoing Activity : 4 Nos
- Completed Activity : 8
- Percentage Completion : 40%
- SPI – Scheduled Performance Index : 1.9
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 13
29/04/2026
- Total Planned Activity : 20 nos
- Ongoing Activity : 4 Nos
- Completed Activity : 8
- Percentage Completion : 40%
- SPI – Scheduled Performance Index : 2.1
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 14
30/04/2026
- Total Planned Activity : 20 nos
- Ongoing Activity : 4 Nos
- Completed Activity : 8
- Percentage Completion : 40%
- SPI – Scheduled Performance Index : 2.0
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 15
02/05/2026
- Total Planned Activity : 20 nos
- Ongoing Activity : 4 Nos
- Completed Activity :9
- Percentage Completion : 45%
- SPI – Scheduled Performance Index : 1.9
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 16
03/05/2026
- Total Planned Activity : 20 nos
- Ongoing Activity : 4 Nos
- Completed Activity : 9
- Percentage Completion : 45%
- SPI – Scheduled Performance Index : 1.8
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 17
04/05/2026
- Total Planned Activity : 20 nos
- Ongoing Activity : 4 Nos
- Completed Activity : 9
- Percentage Completion : 45%
- SPI – Scheduled Performance Index : 1.7
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 18
05/05/2026
- Total Planned Activity : 20 nos
- Ongoing Activity : 4 Nos
- Completed Activity : 9
- Percentage Completion : 45%
- SPI – Scheduled Performance Index : 1.6
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 19
06/05/2026
- Total Planned Activity : 20 nos
- Ongoing Activity : 4 Nos
- Completed Activity : 9
- Percentage Completion : 45%
- SPI – Scheduled Performance Index : 1.5
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 20
07/05/26
- Total Planned Activity : 20 nos
- Ongoing Activity :4 Nos
- Completed Activity : 9
- Percentage Completion : 45%
- SPI – Scheduled Performance Index : 1.5
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 21
08/05/26
- Total Planned Activity : 20 nos
- Ongoing Activity : 4 Nos
- Completed Activity : 9
- Percentage Completion : 45%
- SPI – Scheduled Performance Index : 1.4
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 22
09/05/26
- Total Planned Activity : 20 nos
- Ongoing Activity : 4 Nos
- Completed Activity : 9
- Percentage Completion : 45%
- SPI – Scheduled Performance Index : 1.3
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 23
11/05/26
- Total Planned Activity :20 nos
- Ongoing Activity : 6 Nos
- Completed Activity : 9
- Percentage Completion : 45%
- SPI – Scheduled Performance Index : 1.4
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 24
12/05/26
- Total Planned Activity : 20 nos
- Ongoing Activity : 6 Nos
- Completed Activity : 9
- Percentage Completion : 45%
- SPI – Scheduled Performance Index : 1.5
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 25
13/05/26
- Total Planned Activity : 20 nos
- Ongoing Activity : 6 Nos
- Completed Activity : 9
- Percentage Completion : 45%
- SPI – Scheduled Performance Index : 1.4
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 26
14/05/26
- Total Planned Activity : 20 nos
- Ongoing Activity : 5 Nos
- Completed Activity : 10
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 0.26
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 27
15/05/26
- Total Planned Activity : 20 nos
- Ongoing Activity : 5 Nos
- Completed Activity : 10
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 0.27
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 28
16/05/26
- Total Planned Activity : 20 nos
- Ongoing Activity : 5 Nos
- Completed Activity : 10
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 0.28
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 29
18/05/26
- Total Planned Activity : 20 nos
- Ongoing Activity : 4 Nos
- Completed Activity : 10
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 0.35
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 30
19/05/26
- Total Planned Activity : 20 nos
- Ongoing Activity : 4
- Completed Activity : 10
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 1.0
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 31
20/05/26
- Total Planned Activity : 20 nos
- Ongoing Activity : 4
- Completed Activity : 10
- Percentage Completion : 50%
- SPI – Scheduled Performance Index : 0.36
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 32
21/05/26
- Total Planned Activity : 20 nos
- Ongoing Activity : 4
- Completed Activity : 11
- Percentage Completion : 55%
- SPI – Scheduled Performance Index :0.40
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 33
22/05/26
- Total Planned Activity : 20 nos
- Ongoing Activity : 4
- Completed Activity : 11
- Percentage Completion : 55%
- SPI – Scheduled Performance Index : 0.40
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 34
23/05/26
- Total Planned Activity : 20 nos
- Ongoing Activity : 4
- Completed Activity : 11
- Percentage Completion :55%
- SPI – Scheduled Performance Index : 0.40
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 35
25/05/26
- Total Planned Activity : 20 nos
- Ongoing Activity : 4
- Completed Activity : 11
- Percentage Completion :55%
- SPI – Scheduled Performance Index : 0.40
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 36
26/05/26
- Total Planned Activity : 20 nos
- Ongoing Activity : 4
- Completed Activity : 11
- Percentage Completion : 55%
- SPI – Scheduled Performance Index : 0.40
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 37
27/05/26
- Total Planned Activity : 20 nos
- Ongoing Activity : 4
- Completed Activity : 12
- Percentage Completion : 60%
- SPI – Scheduled Performance Index : 0.44
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 38
29/05/26
- Total Planned Activity : 20 nos
- Ongoing Activity : 4
- Completed Activity : 12
- Percentage Completion : 60%
- SPI – Scheduled Performance Index : 0.44
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 39
30/05/26
- Total Planned Activity : 20 nos
- Ongoing Activity : 4
- Completed Activity : 12
- Percentage Completion : 60%
- SPI – Scheduled Performance Index : 0.47
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 40
01/06/26
- Total Planned Activity : 20nos
- Ongoing Activity : 4
- Completed Activity : 14
- Percentage Completion : 70%
- SPI – Scheduled Performance Index : 0.57
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 41
02/06/26
- Total Planned Activity :20 nos
- Ongoing Activity : 3
- Completed Activity : 17
- Percentage Completion : 70%
- SPI – Scheduled Performance Index : 0.44
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 42
03/06/26
- Total Planned Activity : 20nos
- Ongoing Activity : 3
- Completed Activity : 17
- Percentage Completion : 70%
- SPI – Scheduled Performance Index : 0.43
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)



Day 43
04/06/26
- Total Planned Activity : 20
- Ongoing Activity : 3
- Completed Activity :17
- Percentage Completion : 85
- SPI – Scheduled Performance Index : 0.62
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 44
05/06/26
- Total Planned Activity : 20
- Ongoing Activity : 3 Nos
- Completed Activity : 17
- Percentage Completion : 85
- SPI – Scheduled Performance Index : 0.62
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 45
06/06/26
- Total Planned Activity : 20
- Ongoing Activity : 3 Nos
- Completed Activity : 17
- Percentage Completion : 85%
- SPI – Scheduled Performance Index : 0.62
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 46
06/06/26
- Total Planned Activity : 20
- Ongoing Activity : 3 Nos
- Completed Activity : 17
- Percentage Completion : 85%
- SPI – Scheduled Performance Index : 0.62
If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)


Day 47
Day 48
Day 49
Day 50
Day 51
Day 52
Day 53
Day 54
Day 55
Day 56
Day 57
Day 58
Day 59
Day 60


