SRD & Stem Complex

Improving stem drying efficiency and process control through optimized equipment layout and enhanced automation integration.

Gantt Chart for SRD & Stem Complex

Day 01

16/04/2026 (Thursday)

Stem Dryer Doors 16 No’s Removing Work. Stem Dryer Cooler Duct Removing. Stem complex Bleed Line Ducts Removing.

17/04/2026

Stem Dryer Front Face Conveyors Supports Dismateling .Stem Dryer Apron Removing.(Total 212 Repers 8’11″/9″ Size)

18/04/2026

Strem Coplex Duct Removing.Stem Vibrator 3&4 Shifting. Total Stem Complex Structers And Jackeys With 200 Channel Fixed Under Legs.

21/04/2026

Stem Thins Fan With Saperator Shifting Stem Vib 1 & 2 Delivery Conveyor Shifting Fan Ducts Shfiting Small Stair Case & Supports Shifting Works Done Bt Crane.

22/04/2026

Stem Main Lifting Fan Shifting. Total Stem Complex Platform Shifting.

23/04/2026

Stem Redryer Moment 60′ Feet Forward  From Its Existing Position.Stem Press & Power Pack Shifting From Its Existing Position.

24/04/2026

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 2 Nos
  • Completed Activity : 1
  • Percentage Completion : 5.6%
  • SPI – Scheduled Performance Index : 2.2

 

25/04/2026

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 1Nos
  • Completed Activity : 2
  • Percentage Completion : 11.1%
  • SPI – Scheduled Performance Index : 2.1

 

27/04/2026

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 2 Nos
  • Completed Activity : 2
  • Percentage Completion : 11.1%
  • SPI – Scheduled Performance Index : 1.9

 

28/04/2026

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 4 Nos
  • Completed Activity : 3
  • Percentage Completion : 16.7%
  • SPI – Scheduled Performance Index : 1.9

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

29/04/2026

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 4 Nos
  • Completed Activity : 3
  • Percentage Completion :16.7%
  • SPI – Scheduled Performance Index : 1.9

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

30/04/2026

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 3
  • Percentage Completion : 16.7%
  • SPI – Scheduled Performance Index : 2.0

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

01/05/2026

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 3
  • Percentage Completion : 16.7%
  • SPI – Scheduled Performance Index : 1.9

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

02/04/2026

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 3
  • Percentage Completion : 16.7%
  • SPI – Scheduled Performance Index : 1.9

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

04/04/2026

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 3
  • Percentage Completion : 16.7%
  • SPI – Scheduled Performance Index : 1.7

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

05/05/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 3
  • Percentage Completion : 16.7%
  • SPI – Scheduled Performance Index : 1.6

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

06/05/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 3
  • Percentage Completion : 16.7%
  • SPI – Scheduled Performance Index : 1.5

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

07/05/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 3
  • Percentage Completion : 16.7%
  • SPI – Scheduled Performance Index : 1.5

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

08/05/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 3
  • Percentage Completion : 16.7%
  • SPI – Scheduled Performance Index : 1.4

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

09/05/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 3
  • Percentage Completion : 16.7%
  • SPI – Scheduled Performance Index : 1.3

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

11/05/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 1
  • Completed Activity : 4
  • Percentage Completion : 22.2%
  • SPI – Scheduled Performance Index : 1.4

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

12/05/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : 4
  • Percentage Completion : 22.2%
  • SPI – Scheduled Performance Index : 1.0

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

13/05/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 1
  • Completed Activity : 4
  • Percentage Completion : 22.2%
  • SPI – Scheduled Performance Index : 1.4

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

14/05/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 2
  • Completed Activity : 7
  • Percentage Completion : 38.9%
  • SPI – Scheduled Performance Index : 1.0

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

15/05/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 2
  • Completed Activity : 7
  • Percentage Completion : 38.9%
  • SPI – Scheduled Performance Index : 0.27

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

16/05/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 2
  • Completed Activity : 7
  • Percentage Completion : 38.9%
  • SPI – Scheduled Performance Index : 1.0

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

18/05/26

  • Total Planned Activity :  18nos
  • Ongoing Activity : 0
  • Completed Activity : 9
  • Percentage Completion :50.0%
  • SPI – Scheduled Performance Index : 0.35

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

19/05/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 1
  • Completed Activity : 9
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.34

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

20/05/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 1
  • Completed Activity : 9
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.36

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

21/05/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 1
  • Completed Activity : 9
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.40

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

22/05/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 1
  • Completed Activity : 9
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.40

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

23/05/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 1
  • Completed Activity : 5
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.40

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

25/05/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 1
  • Completed Activity : 5
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.40

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

26/05/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 1
  • Completed Activity : 6
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.40

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

27/05/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 2
  • Completed Activity : 9
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.44

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

29/05/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 2
  • Completed Activity : 9
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.47

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

30/05/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 2
  • Completed Activity : 9
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.47

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

01/06/26

  • Total Planned Activity : 18 nos
  • Ongoing Activity : 2
  • Completed Activity : 9
  • Percentage Completion : 50%
  • SPI – Scheduled Performance Index : 0.57

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

02.06.2026

  • Total Planned Activity : 15
  • Ongoing Activity : 2
  • Completed Activity :9
  • Percentage Completion : 60%
  • SPI – Scheduled Performance Index :0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

03.06.26

  • Total Planned Activity : 15
  • Ongoing Activity : 2
  • Completed Activity : 9
  • Percentage Completion : 60%
  • SPI – Scheduled Performance Index :0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

04.06.2026

  • Total Planned Activity :15
  • Ongoing Activity : 2
  • Completed Activity : 9
  • Percentage Completion :60%
  • SPI – Scheduled Performance Index :0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

05.06.26

  • Total Planned Activity : 15
  • Ongoing Activity : 2
  • Completed Activity : 9
  • Percentage Completion : 60%
  • SPI – Scheduled Performance Index :0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

06.06.26

  • Total Planned Activity :15
  • Ongoing Activity : 2
  • Completed Activity : 9
  • Percentage Completion : 60%
  • SPI – Scheduled Performance Index :0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

08.06.26

  • Total Planned Activity : 15
  • Ongoing Activity : 3
  • Completed Activity : 9
  • Percentage Completion : 60%
  • SPI – Scheduled Performance Index : 0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

16/04/2026 (Thursday)

  • Total Planned Activity : 42 nos
  • Ongoing Activity : 3 Nos
  • Completed Activity : Nil
  • Percentage Completion : 0%
  • SPI – Scheduled Performance Index : 1.0

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)