LRD & Packing

Strengthening lamina drying and packing systems to ensure quality consistency, higher output, and reliable operations.

Gantt Chart for LRD & Packing

Day 01

16/04/2026 (Thursday)

Lamina Redryer Old Apron Removing Work. 119 Repers Removed.

17/04/2026

Lamina Redryer Old Apron Removing Work. 205 Repers Removed.

18/04/2026

Lamina Redryer Old Apron Removing Work. 92 Repers Removed. Total 416 Old Apron Repers Removing Work Completed.LRD Drive Sprockets With Shaft Removed

20/04/2026

Lamina Redrey Fans Serviceing Work & Motor Beds Stenghting Work .

21/04/2026

Lamina Redrey Fans Serviceing Work & Motor Beds Stenghting Work .

22/04/2026

Lamina Redrey Fans Serviceing Work & Motor Beds Stenghting Work .

23/04/2026

  • Total Planned Activity : 4 nos
  • Ongoing Activity : 1 Nos
  • Completed Activity : Nil
  • Percentage Completion : 0%
  • SPI – Scheduled Performance Index : 1.7

24/04/2026

  • Total Planned Activity : 4 nos
  • Ongoing Activity : 1 Nos
  • Completed Activity : Nil
  • Percentage Completion : 0%
  • SPI – Scheduled Performance Index : 2.2

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

25/04/2026

  • Total Planned Activity : 42 nos
  • Ongoing Activity : 5 Nos
  • Completed Activity : 1
  • Percentage Completion : 25%
  • SPI – Scheduled Performance Index : 2.1

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

27/04/2026

  • Total Planned Activity : 42 nos
  • Ongoing Activity : 5 Nos
  • Completed Activity : 1
  • Percentage Completion : 25%
  • SPI – Scheduled Performance Index : 2.1

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

28/04/2026

  • Total Planned Activity : 42 nos
  • Ongoing Activity : 5Nos
  • Completed Activity : 1
  • Percentage Completion : 25%
  • SPI – Scheduled Performance Index : 1.9

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

30/04/2026

  • Total Planned Activity : 4 nos
  • Ongoing Activity : 1 Nos
  • Completed Activity : 1
  • Percentage Completion : 25%
  • SPI – Scheduled Performance Index : 2.0

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

29/04/2026

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 2 Nos
  • Completed Activity : 1
  • Percentage Completion : 25%
  • SPI – Scheduled Performance Index : 2.1

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

01/05/2026

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 1 Nos
  • Completed Activity : 1
  • Percentage Completion : 0%
  • SPI – Scheduled Performance Index : 1.0

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

02/05/26

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 1
  • Completed Activity : 1
  • Percentage Completion : 25%
  • SPI – Scheduled Performance Index : 1.9

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

04/05/26

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 1
  • Completed Activity : 1
  • Percentage Completion : 25%
  • SPI – Scheduled Performance Index : 1.7

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

05/05/26

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 1
  • Completed Activity : 1
  • Percentage Completion : 25%
  • SPI – Scheduled Performance Index : 1.6

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

06/05/26

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 2
  • Completed Activity : 2
  • Percentage Completion : 20%
  • SPI – Scheduled Performance Index : 1.5

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

07/05/26

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 2
  • Completed Activity : 2
  • Percentage Completion : 20%
  • SPI – Scheduled Performance Index : 1.5

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

08/05/26

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 2
  • Completed Activity :2
  • Percentage Completion : 20%
  • SPI – Scheduled Performance Index : 1.4

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

09/05/26

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 2
  • Completed Activity : 2
  • Percentage Completion : 20%
  • SPI – Scheduled Performance Index : 1.3

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

11/05/26

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 1
  • Completed Activity : 2
  • Percentage Completion : 20%
  • SPI – Scheduled Performance Index : 0.22

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

12/05/26

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 1
  • Completed Activity : 2
  • Percentage Completion : 20%
  • SPI – Scheduled Performance Index : 0.24

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

13/05/26

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 1
  • Completed Activity : 2
  • Percentage Completion : 20%
  • SPI – Scheduled Performance Index :0.25

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

14/05/26

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 2
  • Completed Activity : 3
  • Percentage Completion : 30%
  • SPI – Scheduled Performance Index : 0.26

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

16/05/26

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 2
  • Completed Activity : 3
  • Percentage Completion : 30%
  • SPI – Scheduled Performance Index : 0.28

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

17/05/26

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 2
  • Completed Activity : 3
  • Percentage Completion : 30%
  • SPI – Scheduled Performance Index : 0.29

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

18/05/26

  • Total Planned Activity :10 nos
  • Ongoing Activity : 1
  • Completed Activity : 3
  • Percentage Completion : 30%
  • SPI – Scheduled Performance Index : 0.35

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

19/05/26

  • Total Planned Activity :10 nos
  • Ongoing Activity : 1
  • Completed Activity : 3
  • Percentage Completion : 30%
  • SPI – Scheduled Performance Index : 0.36

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

20/05/26

  • Total Planned Activity : 10nos
  • Ongoing Activity : 1
  • Completed Activity : 3
  • Percentage Completion : 30%
  • SPI – Scheduled Performance Index : 0.36

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

21/05/26

  • Total Planned Activity :10 nos
  • Ongoing Activity : 1
  • Completed Activity : 3
  • Percentage Completion : 30%
  • SPI – Scheduled Performance Index :0.40

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

22/05/26

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 1
  • Completed Activity : 3
  • Percentage Completion : 30%
  • SPI – Scheduled Performance Index : 0.40

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

23/05/26

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 2
  • Completed Activity : 3
  • Percentage Completion : 30%
  • SPI – Scheduled Performance Index : 0.41

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

25/05/26

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 2
  • Completed Activity : 3
  • Percentage Completion : 30%
  • SPI – Scheduled Performance Index : 0.43

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

26/05/26

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 2
  • Completed Activity : 3
  • Percentage Completion : 30%
  • SPI – Scheduled Performance Index : 0.44

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

27/05/26

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 2
  • Completed Activity : 3
  • Percentage Completion : 30%
  • SPI – Scheduled Performance Index : 0.45

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedul

29/05/26

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 2
  • Completed Activity : 3
  • Percentage Completion : 30%
  • SPI – Scheduled Performance Index : 0.47

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

30/05/26

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 2
  • Completed Activity : 3
  • Percentage Completion : 30%
  • SPI – Scheduled Performance Index : 0.47

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule

01/06/26

  • Total Planned Activity : 10 nos
  • Ongoing Activity : 2
  • Completed Activity : 3
  • Percentage Completion : 30%
  • SPI – Scheduled Performance Index : 0.47

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

02.06.2026

  • Total Planned Activity : 11
  • Ongoing Activity : 2
  • Completed Activity : 5
  • Percentage Completion : 46
  • SPI – Scheduled Performance Index: 0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

03.06.2026

  • Total Planned Activity : 11
  • Ongoing Activity : 2
  • Completed Activity : 5
  • Percentage Completion : 46%
  • SPI – Scheduled Performance Index : 0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

04.06.26

  • Total Planned Activity : 11
  • Ongoing Activity : 2
  • Completed Activity : 5
  • Percentage Completion : 46%
  • SPI – Scheduled Performance Index : 0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

05.06.26

  • Total Planned Activity : 11
  • Ongoing Activity : 2
  • Completed Activity : 5
  • Percentage Completion : 46%
  • SPI – Scheduled Performance Index :0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

06.06.26

  • Total Planned Activity :11
  • Ongoing Activity :2
  • Completed Activity : 5
  • Percentage Completion : 46%
  • SPI – Scheduled Performance Index : 0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedule)

08.06.26

  • Total Planned Activity : 11
  • Ongoing Activity : 2
  • Completed Activity :5
  • Percentage Completion : 46%
  • SPI – Scheduled Performance Index : 0.62

If SPI = 1 (OK) if SPI less than 1 (Behind Schedule) if SPI More than 1 (Good – Ahead of Schedul